Skip to content
Public Media NetworkPublic Media NetworkPublic Media Network
  • Local News & Stories
  • Watch
    • TV Schedules
    • Live Streams
    • OnDemand
    • PMN+ App
  • Government
  • Create
    • Find your role at PMN
    • Become a Content Creator
    • Media Arts Lab
    • Youth Media
    • Partner with us
    • mediaImpact
  • Support
    • Donate
    • Volunteer
    • Sponsorship Opportunities
  • Make a difference
Notification Show More
Font ResizerAa
Font ResizerAa
Public Media NetworkPublic Media Network
  • Local News & Stories
  • Watch
  • Government
  • Create
  • Support
  • Make a difference
  • Local News & Stories
  • Watch
    • TV Schedules
    • Live Streams
    • OnDemand
    • PMN+ App
  • Government
  • Create
    • Find your role at PMN
    • Become a Content Creator
    • Media Arts Lab
    • Youth Media
    • Partner with us
    • mediaImpact
  • Support
    • Donate
    • Volunteer
    • Sponsorship Opportunities
  • Make a difference
Public Media Network > Blog > News > Community > Oshtemo Township Advances Solar Moratorium While Drafting Battery Storage Safety Rules
Community

Oshtemo Township Advances Solar Moratorium While Drafting Battery Storage Safety Rules

By
Matt Schuster, PMN Creator
3 weeks ago
3 Min Read
Share
SHARE

Oshtemo Township’s Planning Commission voted unanimously to advance a moratorium on new solar energy project applications to the Township Board.

The moratorium would pause new solar development applications while the commission finishes work on a broader energy systems ordinance covering solar, battery storage, and wind projects. No members of the public spoke at the hearing before the vote. The moratorium now goes to the Township Board for further action.

Much of the meeting focused on the battery storage, or energy storage system (ESS), provisions taking shape in that broader ordinance, driven in part by concerns raised at past meetings about large-scale battery projects proposed in the township. The commission worked through a detailed set of safety requirements for any future ESS facility:

  • Early gas detection. Battery enclosures would need a multi-gas detection system capable of identifying off-gases associated with early-stage thermal runaway — the chemical process that can precede a battery fire — before smoke or flame is visible, targeting gases including hydrogen and carbon monoxide.
  • Automatic fire suppression. Each battery enclosure would need an automatically actuated suppression system, using an agent compatible with the battery chemistry involved, installed by a licensed contractor to NFPA standards and capable of operating on battery power if grid power is lost.
  • Cybersecurity requirements. Because these systems are networked, the ordinance would require access controls such as network segmentation and firewalls to guard against unauthorized access, with the commission agreeing that outside technical experts would need to weigh in on more advanced measures, such as data diodes, given the complexity involved.
  • Groundwater protection. Projects would need a hydrological analysis projecting how groundwater moves from the site, plus long-term annual monitoring for metals, PFAS, and other contaminants.
  • Emergency planning. Facility owners would need to develop an emergency response plan in consultation with the Oshtemo Township Fire Department, kept up to date and shared with the department after any significant changes or incidents.

The commission also discussed wind energy provisions, including a proposed change to broaden protection from turbine shadow flicker to cover all “non-participating properties” near a project, not just occupied residences, so that vacant land that could later be developed is also protected.

Toward the end of the meeting, several residents raised concerns about the potential for a large-scale energy storage project in the township, including property values, insurance adequacy, and decommissioning plans in the event of a fire or partial failure. In response, the commission agreed to reinstate a requirement, present in earlier ordinance drafts but since dropped, that projects proposed on undeveloped land include an analysis of alternative sites, consistent with state guidelines.

No final vote was taken on the broader energy systems ordinance itself; the commission’s discussion and review is ongoing.

TAGGED:energy systems ordinanceoshtemo townshipplanning commissionsolar moratorium
SOURCES:Creator Role [R]Oshtemo Township Planning Commission - September 10, 2026
Share This Article
Facebook Flipboard Pinterest LinkedIn Reddit Email Copy Link Print
Previous Article Members of the zoning board of appeals review a variance request at their meeting in city hall chambers Kalamazoo Zoning Board of Appeals Waives Sidewalk Requirement Along Busy Drake Road Stretch
Next Article Comstock Planning Commissioners discuss the Swan and Cygnet Energy Storage System Comstock Approves Special Land Use Request for Swan and Cygnet Battery Storage Project
- Public Media Network Supports -
Ad image

Public Media Network

  • About
  • Meet the Team
  • Board of Directors
  • History
  • Financials
  • Contact

Watch

  • Live Streams
  • PMN OnDemand
  • PMN+ App
  • Archive

Create

  • Become a Creator
  • Content Studio
  • mediaImpact
  • Media Arts Lab
  • Youth Media
  • Creator Access Portal
  • Share Your Videos

Support

  • Make a difference
  • Volunteer
  • Newsletter
  • PMN Community Partner
Public Media NetworkPublic Media Network
Follow US
359 S. Kalamazoo Mall, Ste 300, Kalamazoo, MI 49007 | 269.343.2211 | Tax ID #38-2564383
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?